Completed Projects

NEW MEXICO MILITARY INSTITUTE
Status of Capital Projects Completed Since July 1, 2006
 
PROJECT TOTAL COST TOTAL CONSTRUCTION COST SOURCE OF FUNDING START DATE COMPLETION DATE
Bates Hall Boiler System Upgrade $109,797 $94,637 $109,797 Infrastructure Fund May-06 Aug-06
JRT Fire Supression $139,000 $131,000 $139,000 Infrastructure Fund May-06 Jul-06
Enrollment & Development Center $3,652,844 $2,881,930 $3,652,844 Daniels Fund Mar-06 Oct-06
Daniels Leadership Center $6,136,912 $5,081,175 $6,136,912 Daniels Fund Jan-06 Oct-06
Godfrey Athletic Training Center Phase I $429,440 $352,946 $429,440 Legislative Allocation Sep-06 Apr-07
Leadership Reaction Course $841,007 $826,579 $841,007 Daniels Fund & Yates Foundation Aug-06 Mar-07
Fitness Factory  $284,164 $284,164 $284,164 Legislative Allocation Sep-06 Apr-07
Godfrey Athletic Training Center Phase II $85,952 $85,952 $85,952 Sell of  Property Dec, 2006 May, 2007
Campus Secondary Electrical Feed $136,438 $85,952 $85,952 BRR Infrastructure Mar, 2007 Sep, 2007
Achievement Street Paving $130,214 $130,214 $130,124 BRR Infrastructure Jul, 2007 Aug, 2007
Stapp Field Lights, Phase I $291,249 $291,249 $291,249 Legislative Allocation Jul, 2007 Oct, 2007
Dow Hall Project $4,500,000 $3,790,242 $3,400,000 G.O. Bond Oct, 2007 Jun, 2009
NE Corner Sign Development $64,433 $85,952 $85,952 NMMI Balances Jan, 2008 Feb, 2009
Hagerman Barracks Re-roof $348,334 $344,149 $348,334 BRR Infrastructure Mar, 2008 Jul, 2008
Toles/ VMV/ Bates Roofing Project $83,741 $78,263 $83,741 BRR Infrastructure Apr, 2008 Jun, 2008
Godfrey Pool Mechanical, Phase I of IV $197,000 $194,256 $65,000 Legislative Allocation Jul, 2008 Aug, 2008